<u><b>NOVEMBER</b></u><br><br><b>74 Birch Rd.</b><br>Week of November 5: sheetrock<br>Week of November 12: install cabinets, hardware, paint interior<br>Week of November 19: sod, final landscaping<br>Week of November 26: completion<br><br><br><b>54 Birch Rd.</b><br>Week of November 5: electrical, plumbing<br>Week of November 12: finish plumbing, exterior paint<br>Week of November 19: sheetrock<br>Week of November 26: install cabinets, hardware, paint interior<br><br><b>37 Davis St.</b><br>Week of November 5: frame<br>Week of November 12: windows, begin roof<br>Week of November 19: shingle roof, exterior walls<br>Week of November 26: electrical, plumbing<br><br>

--------------