HOME | Project Schedule

Project Schedule

NOVEMBER

74 Birch Rd.
Week of November 5: sheetrock
Week of November 12: install cabinets, hardware, paint interior
Week of November 19: sod, final landscaping
Week of November 26: completion


54 Birch Rd.
Week of November 5: electrical, plumbing
Week of November 12: finish plumbing, exterior paint
Week of November 19: sheetrock
Week of November 26: install cabinets, hardware, paint interior

37 Davis St.
Week of November 5: frame
Week of November 12: windows, begin roof
Week of November 19: shingle roof, exterior walls
Week of November 26: electrical, plumbing

--------------